Andes Drive Pump Station Force Main Liningin progress
Status set at the City Council Meeting on Nov 18, 2025
The Andes Drive Pump Station Force Main Lining is a municipal infrastructure project involving the lining and repair of the force main associated with the Andes Drive pump station.
On November 12, 2024, City Council unanimously approved (6-0) awarding a construction contract to J. Fletcher Creamer & Son, Inc. for an estimated $834,892 as part of the consent agenda. On November 18, 2025, Council again unanimously approved a contract modification increasing the contract value by $349,904 to cover replacement of force main infrastructure inside the wet well, additional excavations, and lining of the 8-inch force main.
The modification brought the total project cost to $1,184,796. The project is currently in progress.
Still open
- Project completion and final closeout have not yet been recorded in the available material.
Discussion time
councilcommissionMinutes of named discussion per transcribed meeting, Nov 12, 2024 onward.
History
Filled dots are actions on this topic; open dots are mentions.
- Award of Construction Contract – Andes Drive Pump Station Force Main Lining
Construction contract awarded to J. Fletcher Creamer & Son, Inc. for an estimated amount of $834,892.
passedAward of construction contract to J. Fletcher Creamer & Son, Inc. for Andes Drive Pump Station Force Main Lining ($834,892).✓ Bates✓ Doyle Feingold✓ Greenfield✓ Lim✓ Ross✓ Stehle - Consideration of a contract modification for the Andes Drive Pump Station Main Lining to increase the contract value by $349,904
Council approved a contract modification increasing the contract value by $349,904 (to a total of $1,184,796) to cover replacement of force main infrastructure inside the wet well and additional excavations and lining of the 8-inch force main.
passedMotion to approve a contract modification for the Andes Drive Pump Station main lining to increase the contract value by $349,904.✓ Amos✓ Bates✓ Hall✓ Hardy-Chandler✓ McQuillen✓ Peterson