project

Andes Drive Pump Station Force Main Lining

in progress

Status set at City Council Meeting on Nov 18, 2025

Project wiki — a maintained overview, meeting history, and recorded positions.

  1. Proposed
  2. Under review
    Nov 18, 2025
  3. Decided
    Nov 12, 2024

Summary

The Andes Drive Pump Station Force Main Lining is a stormwater/sewer infrastructure project involving the lining and rehabilitation of the force main associated with the Andes Drive pump station. On November 12, 2024, the City Council unanimously approved (6-0) award of the initial construction contract to J. Fletcher Creamer & Son, Inc. for an estimated $834,892 as part of the consent agenda. After work commenced, additional infrastructure needs were identified, including replacement of force main infrastructure inside the wet well and additional excavations and lining of the 8-inch force main. On November 18, 2025, the Council unanimously approved (6-0) a contract modification increasing the contract value by $349,904, bringing the total project cost to $1,184,796. The project is managed in coordination with the stormwater utility program and is currently in progress under the modified contract.

Open questions & options on the table

  • Construction and rehabilitation work under the modified contract is ongoing; project completion has not yet been recorded.

What members have said

Hardy-Chandler

On November 18, 2025, Council Member Hardy-Chandler made the motion to approve the contract modification increasing the Andes Drive Pump Station main lining contract value by $349,904.

Peterson

On November 18, 2025, Council Member Peterson seconded the motion to approve the contract modification.

Positions as recorded in meeting minutes; votes without recorded comment aren’t summarized.

Discussion time

Minutes of named discussion per transcribed meeting.

Full history

  1. Nov 12, 2024City Council· item 8dapproved#

    [8d] Construction contract awarded to J. Fletcher Creamer & Son, Inc. for an estimated amount of $834,892.

    passedAward of construction contract to J. Fletcher Creamer & Son, Inc. for Andes Drive Pump Station Force Main Lining ($834,892).
    Bates Doyle Feingold Greenfield Lim Ross Stehle
  2. Nov 18, 2025City Council· item 10ain progress#

    [10a] Council approved a contract modification increasing the contract value by $349,904 (to a total of $1,184,796) to cover replacement of force main infrastructure inside the wet well and additional excavations and lining of the 8-inch force main.

    passedMotion to approve a contract modification for the Andes Drive Pump Station main lining to increase the contract value by $349,904.
    Amos Bates Hall Hardy-Chandler McQuillen Peterson