Andes Drive Pump Station Force Main Lining
in progressStatus set at City Council Meeting on Nov 18, 2025
Project wiki — a maintained overview, meeting history, and recorded positions.
- Proposed
- Under reviewNov 18, 2025
- DecidedNov 12, 2024
Summary
The Andes Drive Pump Station Force Main Lining is a stormwater/sewer infrastructure project involving the lining and rehabilitation of the force main associated with the Andes Drive pump station. On November 12, 2024, the City Council unanimously approved (6-0) award of the initial construction contract to J. Fletcher Creamer & Son, Inc. for an estimated $834,892 as part of the consent agenda. After work commenced, additional infrastructure needs were identified, including replacement of force main infrastructure inside the wet well and additional excavations and lining of the 8-inch force main. On November 18, 2025, the Council unanimously approved (6-0) a contract modification increasing the contract value by $349,904, bringing the total project cost to $1,184,796. The project is managed in coordination with the stormwater utility program and is currently in progress under the modified contract.
Open questions & options on the table
- Construction and rehabilitation work under the modified contract is ongoing; project completion has not yet been recorded.
What members have said
On November 18, 2025, Council Member Hardy-Chandler made the motion to approve the contract modification increasing the Andes Drive Pump Station main lining contract value by $349,904.
On November 18, 2025, Council Member Peterson seconded the motion to approve the contract modification.
Positions as recorded in meeting minutes; votes without recorded comment aren’t summarized.
Discussion time
Minutes of named discussion per transcribed meeting.
Full history
[8d] Construction contract awarded to J. Fletcher Creamer & Son, Inc. for an estimated amount of $834,892.
passedAward of construction contract to J. Fletcher Creamer & Son, Inc. for Andes Drive Pump Station Force Main Lining ($834,892).✓ Bates✓ Doyle Feingold✓ Greenfield✓ Lim✓ Ross✓ Stehle[10a] Council approved a contract modification increasing the contract value by $349,904 (to a total of $1,184,796) to cover replacement of force main infrastructure inside the wet well and additional excavations and lining of the 8-inch force main.
passedMotion to approve a contract modification for the Andes Drive Pump Station main lining to increase the contract value by $349,904.✓ Amos✓ Bates✓ Hall✓ Hardy-Chandler✓ McQuillen✓ Peterson