Andes Drive Pump Station Main Lining

in progress

Recent updates

Nov 18, 2025City Council ยท item 10ain progress

[10a] Council approved a contract modification increasing the contract value by $349,904 (to a total of $1,184,796) to cover replacement of force main infrastructure inside the wet well and additional excavations and lining of the 8-inch force main.

Full history

  1. Nov 18, 2025City Council ยท item 10ain progress

    [10a] Council approved a contract modification increasing the contract value by $349,904 (to a total of $1,184,796) to cover replacement of force main infrastructure inside the wet well and additional excavations and lining of the 8-inch force main.