Fairfax HS Electrical Program Build-Out

The Fairfax HS Electrical Program Build-Out is a Schools Capital Improvement Program (CIP) project requiring a reappropriation of funds to support the construction or expansion of an electrical program facility at Fairfax High School.

The Providence ES Vestibule is a Schools Capital Improvement Program (CIP) project requiring a reappropriation of funds. The project was first discussed at the City Council Work Session on November 4, 2025, as part of a broader agenda item that also covered a reappropriation for an electrical program build-out at Fairfax HS and a 0.5 FTE addition to the Schools Superintendent position.

  • Discussion on Reappropriation Resolution for Schools CIP Projects and 0.5 FTE Addition to Schools Superintendent Position

    A reappropriation resolution related to the electrical program build-out at Fairfax HS was discussed at this work session; no formal vote was recorded.

  • Nov 18, 2025City Council · item 6gapproved
    Consideration of a reappropriation resolution related to Schools CIP projects for Providence ES vestibule and electrical program build-out at Fairfax HS, and approval of 0.5 FTE addition to the Schools Superintendent position

    A reappropriation resolution covering the electrical program build-out at Fairfax HS was approved as part of the consent agenda.

In full

The matter was first discussed at the November 4, 2025 City Council Work Session as part of a broader agenda item that also addressed a reappropriation for Providence ES vestibule improvements and a 0.5 FTE addition to the Schools Superintendent position; no formal vote was taken at that session. On November 18, 2025, the City Council approved the reappropriation resolution covering the Fairfax HS electrical program build-out as part of the consent agenda, unanimously. The project is now approved and funded through the reappropriation.