Skip to content
CouncilHound
← Projects & topics
Project · on the record since 2025

Pat Rodio Playground

The Pat Rodio Playground is a parks capital project funded at $400,000, with $315,000 allocated for equipment and surfacing and the remainder designated for fencing, walkways, and trees.

in progress

Thaiss Park is a City park undergoing a full redevelopment project contracted to Bright Masonry, Inc. for $7,725,650, approved by City Council on October 8, 2024. Construction began in December 2024 following utility relocation work and full park closure; the cross-county trail was kept open but made inaccessible from the park during construction.

Other mentions

In full

Following a public survey (results reported June 12, 2025) that showed strong preference for swings, and PRAB's selection of color option 6 from 12 choices, the equipment order was placed before a July 1, 2025 tariff deadline, with shade structures added to the design. Although equipment was initially on back order as of September 2025, it arrived ahead of schedule and installation was underway by October 2025. By November 13, 2025, the playground structure itself had been installed, with fencing, walkways, landscaping, and new code-of-conduct signage still pending.

No separate Pat Rodio Playground update appeared in the July 9, 2026 PRAB meeting minutes, suggesting those remaining site work items may still be outstanding or were completed without further board-level reporting.