Transform 66 Outside the Beltway Concession Funding
The Transform 66 Outside the Beltway Concession Funding item concerns a proposed $4.6 million supplemental appropriation for the George Snyder Trail, drawn from the Transform 66 concessionaire balance entry account at VDOT, as recommended by the Northern Virginia Transportation Authority (NVTA).
George Snyder Trail
The George Snyder Trail was a planned off-street shared-use path project (VDOT UPC 112816) intended to improve multimodal connectivity along Fairfax Boulevard in the City of Fairfax. The project drew sustained and significant public opposition throughout its consideration.
- Dec 9, 2025City Council · item 6iIntroduction of a grant supplemental appropriation resolution in the amount of $4,600,000 for Transform 66 Outside the Beltway Concession Funding for the George Snyder Trail
The City requested and received NVTA recommendation for an additional $4.6 million from the Transform 66 concessionaire balance entry account at VDOT; final CTB approval is scheduled for January 6, 2026.
passedIntroduce the supplemental appropriation resolution of $4,600,000 from Transform 66 Outside the Beltway Concession Funding for the George Snyder Trail, waive the first reading, and set the public hearing for January 13, 2026.✓ Amos✓ Bates– Hall✓ Hardy-Chandler✕ McQuillen✕ Peterson - Jan 13, 2026City Council · item 7ePublic Hearing and Council Action on a Grant Supplemental Appropriation Resolution – $4,600,000 from Transform 66 Outside the Beltway Concession Funding for the George Snyder Trail
The resolution to appropriate an additional $4.6 million in Transform 66 Outside the Beltway Concession Funding for the George Snyder Trail failed by a 3-3 vote.
failedApprove the supplemental appropriation resolution in the amount of $4,600,000 from Transform 66 Outside the Beltway Concession Funding for the George Snyder Trail✓ Amos✓ Bates✕ Hall✓ Hardy-Chandler✕ McQuillen✕ Peterson
In full
On December 9, 2025, the City Council voted 3-2-1 (Amos, Bates, and Hardy-Chandler in favor; McQuillen and Peterson opposed; Hall abstaining) to introduce the supplemental appropriation resolution, waive the first reading, and set a public hearing for January 13, 2026. Final approval by the Commonwealth Transportation Board (CTB) of the underlying funding was scheduled for January 6, 2026. At the January 13, 2026 public hearing, the appropriation resolution came to a final vote but failed 3-3, with Amos, Bates, and Hardy-Chandler voting yes and Hall, McQuillen, and Peterson voting no.
As a result, the $4.6 million appropriation was not approved. The project had drawn public comment, including a statement of strong support from the Central Fairfax Chamber of Commerce citing economic development and fiscal responsibility.