Development project

Fairfax Old Town Hall Rehabilitation

City Project · 3999 University Dr., Fairfax, VA 22030 · topic history · city record ↗ · on the map

A maintained knowledge base built from council meetings and official records — updated as new meetings land. Last synced Nov 2, 2026.

Overview

through Jul 19, 2026
From the recordNot yet reviewedMay have changed at the Nov 7 meeting

Official record

The city is rehabilitating Old Town Hall, the premier public facility and cultural center of Fairfax for over 125 years. Phase 2 focuses on interior improvements, ADA accessibility, safety and sustainability upgrades, and rear addition modernization. Construction began August 2025 with anticipated completion June 2026.

  • Address: 3999 University Dr., Fairfax, VA 22030
  • City record

Meeting history

through Jul 22, 2025
From the recordNot yet reviewedMay have changed at the Nov 7 meeting

2025-02-10 — Planning Commission Regular Meeting/Work Session

Agenda item 11: Commission Comments (watch the moment)

  • Outcome: Commissioners offered brief comments. Commissioner Rice noted the upcoming PRAB meeting and that Old Town Hall will be offline approximately twelve months for renovations. Chair Feather reported attending a 'Breakfast with the Chairs' meeting and noted an upcoming meeting with the Economic Development Office.
  • [11] Commissioner Rice reported that Old Town Hall will be offline for approximately twelve months due to renovations.

2025-04-08 — City Council Meeting

Agenda item 10a: Work Session: Discussion and Update on Old Town Hall (3999 University Drive) Renovation Project

  • Outcome: Rescheduled for the April 22, 2025 Work Session; no discussion held at this meeting.
  • [10a] Work session discussion on the Old Town Hall (3999 University Drive) renovation project was rescheduled to April 22, 2025.
  • Status after: deferred

2025-06-24 — City Council Meeting

Agenda item 11a: Work Session: Presentation update on Old Town Hall project (watch the moment)

  • Outcome: Presentation given during work session. No formal Council action recorded.
  • [11a] Staff provided a presentation update on the Old Town Hall project during the work session; no formal action was taken.

2025-07-22 — City Council Meeting

Agenda item 6: Consent Agenda (watch the moment)

  • Outcome: Approved unanimously. Included approval of multiple sets of prior meeting minutes and award of contract to A.P. Construction, LLC for the Old Town Hall Phase 2 Rehabilitation project.
  • Vote (passed): Approve the full consent agenda (items 6a–6e). — Amos: yes, Bates: yes, Hall: yes, Hardy-Chandler: no, McQuillen: yes, Peterson: yes
  • [6] Council awarded a contract in the estimated amount of $2,498,800.80 to A.P. Construction, LLC for the Old Town Hall Phase 2 Rehabilitation project.
  • Status after: in_progress

Positions & open questions

through Jul 19, 2026
From the recordNot yet reviewedMay have changed at the Nov 7 meeting

Open questions

No unresolved questions recorded.

Member commentary

No recorded member positions yet.

Page history

Log

2026-07-19

  • Seeded from the tracker profile and official records.

2026-07-28

  • Pipeline refresh.
  • Pipeline refresh.
  • Meeting history updated through 2025-07-22.

2026-07-30

  • Pipeline refresh.

2026-08-04

  • Meeting history updated through 2025-07-22.

2026-09-19

  • Meeting history updated through 2025-07-22.