Skip to content
CouncilHound
← Projects & topics
Place · on the record since 2024 · discussed in 2 transcribed meetings

Andes Drive

The Andes Drive Pump Station Force Main Lining is a municipal infrastructure project involving the lining and repair of the force main associated with the Andes Drive pump station. On November 12, 2024, City Council unanimously approved (6-0) awarding a construction contract to J.

  • Award of Construction Contract – Andes Drive Pump Station Force Main Lining

    Location of the pump station force main lining project for which a construction contract was approved.

    passedAward of construction contract to J. Fletcher Creamer & Son, Inc. for Andes Drive Pump Station Force Main Lining ($834,892).
    ✓ Bates✓ Doyle Feingold✓ Greenfield✓ Lim✓ Ross✓ Stehle