Dwight Avenue Improvements
in progressStatus set at City Council Meeting on Sep 9, 2025 · ▶ watch the moment
Project wiki — a maintained overview, meeting history, and recorded positions.
- Proposed
- Under reviewMay 13, 2025
- Decided
Summary
The Dwight Avenue Improvements project involves intersection realignment at the Sager/Roberts/Dwight intersection and construction of new sidewalk, curb, and gutter on the north side of Dwight Avenue between Roberts Road and Orchard Drive. The project was identified as a new facility/substantial improvement project as of at least December 2024. On May 13, 2025, City Council unanimously adopted Resolution R-25-09, endorsing submission of the Dwight Avenue Improvements—along with 1st/2nd Street Sidewalks and the Northfax East-West Roadway—to VDOT for Revenue Sharing Funding. On September 9, 2025, the Council unanimously adopted an updated resolution (R-25-27) reaffirming submission of the same three projects to VDOT for Revenue Sharing Funding, with an updated application total of up to $10 million. The project is currently in progress and awaiting VDOT funding decisions.
Official city record
City Project
Intersection and sidewalk improvements on Dwight Avenue between Roberts Road and Orchard Drive will enhance pedestrian safety and stormwater management.
Open questions & options on the table
- VDOT's decision on the Revenue Sharing Funding application (submitted per R-25-27, up to $10M total across three projects) is pending.
- Design, procurement, and construction timelines have not yet been established in the record.
What members have said
On September 9, 2025, Councilmember Peterson moved to adopt the updated resolution (R-25-27) approving the city's submission of the three projects—including Dwight Avenue Improvements—to VDOT for Revenue Sharing Funding.
Positions as recorded in meeting minutes; votes without recorded comment aren’t summarized.
Discussion time
Minutes of named discussion per transcribed meeting.
Full history
[8c] Council approved submission to VDOT for Revenue Sharing Funding; project involves intersection realignment at Sager/Roberts/Dwight and new sidewalk, curb and gutter on the north side of Dwight Avenue between Roberts Road and Orchard Drive.
passedEndorsement of R-25-08 (Transportation Alternatives application for Norman Avenue Sidewalk Project) and adoption of R-25-09 (Revenue Sharing applications for three projects)✓ Amos✓ Bates✓ Hall✓ Hardy-Chandler✓ McQuillen✓ Peterson[6i] Included in the updated Revenue Sharing Funding application submitted to VDOT per Resolution R-25-27.
passedAdopt updated resolution R-25-27 to approve the city's submission of three projects — 1st/2nd Street sidewalks, Dwight Avenue improvements, and Northfax East-West roadway — to VDOT for Revenue Sharing Funding.✓ Amos✓ Bates✓ Hall✓ Hardy-Chandler✓ McQuillen✓ Peterson
Discussed alongside
Topics that come up in the same meetings.