Project · on the record since 2024

KJM Turf

The KJM Turf project is a long-running effort (at least 10 years in development) to renovate the KJM athletic fields, with options for either synthetic or natural turf. 5 separate matters touch this project; each has its own status.

Daniels Run Elementary School is undergoing a major renovation project in the City of Fairfax. Key early steps included a Board-approved reallocation of CIP funds (April 7, 2025) to complete a vestibule security project, contingent on FCPS approval for the City to reimburse FCPS for executing the work.

in progress

Pat Rodio Park is a municipal park that has been undergoing a playground relocation and broader redevelopment effort. As of October 2024, staff began seeking a new playground location; by November 2024 a site had been identified, with tree planting and public outreach planned.

in progress

The Van Dyck Redevelopment is a funded parks project in the City's capital pipeline that has been in a holding pattern tied to sequencing with other major construction efforts. Through late 2024, the project was placed on hold pending the start of Thaiss Park construction, with no substantive engineering activity.

in progress

The Fire Station project (commonly referred to in connection with Fire Station 3) is a planned new fire station construction in the City of Fairfax, identified as a capital expenditure to be funded through the $54.5 million revenue bond issuance approved unanimously by City Council on November 12, 2024 (Resolution R-24-32). The Planning Commission was reviewing Fire Station 3 improvements as part of the Capital Improvement Program (CIP), with recommendations expected in January 2025 per a December 2024 PRAB update.

in progress
  • Project Updates – Master Plan, Pat Rodio, Van Dyck Redevelopment, Old Town Renovation, KJM Turf

    Staff is working with Timmons to develop preliminary plans with a more detailed budget for both synthetic and natural turf options.

Other mentions

In full

As of October 2024, staff was working with consultant Timmons to develop preliminary plans and a detailed budget for both options. The project was placed on hold in November 2024 pending the start of Thaiss Park construction, but by December 2024 a 30% design proposal was being reviewed by the City's engineer to better determine pricing. In January 2025, the project was placed on hold again pending action by the new City Council.

As of February 2025, $4 million is allocated and a Timmons proposal covers both turf options, but a decision on one option is needed to avoid additional planning costs. The full Timmons plan — including two turf fields, a track, and a paved area — is estimated at approximately $10 million; $6 million in funding is currently identified ($4M existing plus $2M ARPA), leaving a gap of $6–8 million. At the May 19, 2025 joint PRAB/School Board meeting, PRAB asked the School Board to partner on the project as a joint effort given the fields are shared space.

Construction is estimated to take 16–18 months, or less if synthetic turf is selected.