The City of Fairfax's Stormwater Utility was established on December 14, 2021, with an initial rate of $28.80 per billable unit. Since then, annual rate increases have averaged approximately 6%. A work session discussion scheduled for February 25, 2025 was deferred, and a subsequent work session on May 13, 2025 resulted in no action. On March 24, 2026, staff and consultants from Davenport (a 25-year city financial partner) presented a stormwater utility update as part of a broader FY27 budget work session covering capital improvement, stormwater, and wastewater funds. A public hearing on a proposed 5% rate increase — setting the rate at $36.02 per billable unit for calendar year 2026 — was held on April 28, 2026, with no action taken that night. On May 5, 2026, the City Council unanimously approved the ordinance amending Chapter 102, Article 5, Section 102-203B to set the stormwater utility rate at $36.02 per billable unit effective January 1, 2026; user fees at that rate are projected to generate approximately $3.4 million, reflecting an increase of roughly $162,000 over the prior year.

Open questions & options on the table

  • Stormwater utility credit for storm drain marking (e.g., 'only rain down the drain' program) — staff indicated they would verify whether this credit is still active (May 12, 2026).
  • Staffing capacity to implement stormwater utility-funded programs, including urban forestry initiatives, was identified as an ongoing constraint as of July 14, 2026.

What members have said

Council Member Hardy-Chandler

Made the motion on May 5, 2026 to approve the ordinance setting the stormwater utility rate at $36.02 per billable unit, and also moved to adopt the stormwater utility fund as part of the broader FY27 budget adoption.

Council Member Peterson

Seconded the motion on May 5, 2026 to approve the ordinance setting the stormwater utility rate at $36.02 per billable unit.

Positions as recorded in meeting minutes; votes without recorded comment aren’t summarized.

Discussion time

Minutes of named discussion per transcribed meeting.

Full history

  1. [12d] The work session discussion and update on the Stormwater Utility was deferred to a future date.

  2. [12c] Council received a discussion and update on the Stormwater Utility in work session; no action taken.